The essential difference between CPM and PERT is

A.Critical Path vs. Critical Activity
B.Arrow notation vs. Precedence notation
C.Deterministic approach vs. Probabilistic approach
D.Project Management vs. Network Analysis
Project Formulation, Appraisal and Management
2

The minimum thickness of a wall where single Flemish bond can be used is

A.Half-brick thick
B.One-brick thick
C.One-and-half-brick thick
D.Two-brick thick
Site and Land Development
3

On the colour wheel, the combination of 'Violet-Yellow' or 'Orange-Blue' are best described as

A.Complementary
B.Supplementary
C.Analogous
D.Monochromatic
Landscape Planning and Design
4

The sudden stoppage in the flow of water in a closed conduit results in a phenomenon called

A.Cavitation
B.Hydraulic gradient
C.Stack pressure
D.Water hammer
Water Security and Planning
5

The number of intersecting arches that support Bijapur's Gol Gumbaz is

A.4
B.8
C.12
D.16
Heritage, Renewal and Redevelopment
6
Unlock to reveal
7
Unlock to reveal
8
Unlock to reveal

55 more questions unlocked after purchase

₹0
one-time · lifetime access
  • Full paper access
  • Exam mode (timed)
  • Practice mode
  • Step-by-step explanations
  • Concept knowledge panels
  • Topic-wise analytics
Trusted by planning students
Secure payment · Instant access

Or get all papers with the Monthly Pass (₹199)